Chevron Strikes Power Deal With Microsoft for West Texas AI Data Center

AI总结

核心结论

  • 能源与科技跨界整合:雪佛龙(Chevron)与微软达成20年电力供应协议,旨在为德州大型AI数据中心提供自供能源,标志着能源企业深耕数据中心建设及电力市场的新趋势。
  • Chevron and Microsoft signed a 20-year power deal for a massive AI data center in Texas, highlighting a trend where energy giants directly support tech firms’ power needs.

结构逻辑

  • 业务合作:雪佛龙与Joulent合作,利用Permian盆地的天然气为微软Project Kilby项目供电。
  • 行业动向:油气巨头(如Exxon Mobil)积极抢占AI能源市场,通过天然气供电规避电网建设缓慢的难题。
  • 技术与挑战:数据中心采用“自带电力(BYOP)”模式,建设独立电厂以确保能源供给的确定性与速度。

关键信息

  • 项目名称:Project Kilby (2.7 GW capacity)
  • 地理位置:Reeves County, West Texas
  • 相关方:Chevron, Microsoft, Joulent (Engine No. 1), GE Vernova
  • 交付时间:2028年末启动
  • 行业趋势:AI数据中心缺电危机、能源公司转型、分布式电力供应

问题与回答

  • Q: 为什么科技巨头选择与能源公司直接合作供电?
    A: 因AI高功耗需求超出电网负荷,通过油气田自建电厂可实现能源供应的确定性与速度(BYOP模式)。
  • Q: Chevron在其中的角色是什么?
    A: 利用其Permian盆地的天然气供应与基础设施,为数据中心提供可靠、具竞争力的能源。

正文

A man cleans a car windshield at a Chevron gas station in Pasadena, California, with gas prices displayed as $6.59 for regular, $6.78 for plus, $6.98 for supreme, and $7.99 for diesel.

A man cleans a car windshield at a Chevron gas station in Pasadena, California, with gas prices displayed as $6.59 for regular, $6.78 for plus, $6.98 for supreme, and $7.99 for diesel.

The deal cements Chevron’s lead among major oil companies betting on the data-center boom. Mario Tama/Getty Images

Quick Summary

  • Chevron struck a 20-year agreement to sell electricity to Microsoft for a 2.7-gigawatt AI data center in West Texas.
  • Project Kilby will use an on-site gas-fired power plant fueled by Chevron’s natural gas, initially without a grid connection.
  • The project, a collaboration with Joulent, addresses soaring electricity demand for AI, with power delivery starting in late 2028.

This summary was generated with AI and reviewed by an editor. about how we use artificial intelligence in our journalism.

Chevron CVX 0.57%increase; green up pointing triangle has struck a 20-year agreement to sell electricity to Microsoft MSFT 1.69%increase; green up pointing triangle, which plans to build what could become one of the country’s largest artificial-intelligence data centers in West Texas.

The oil company is working with Joulent, an energy company launched by investment firm Engine No. 1, to build a massive power-generation complex that will supply the data center using natural gas produced from the company’s fields in the area. The 2.7-gigawatt campus would be on more than 2,000 acres in Reeves County in the heart of the Permian Basin oil-and-gas field, according to Joulent.

The companies didn’t disclose a cost estimate for what they call Project Kilby. Chevron expects to make a final investment decision on building a gas-fired power plant for the project after it acquires necessary permits later this year.

The collaboration between Chevron and Joulent is their first big AI data-center project. It is also the latest example of energy companies capturing demand as tech giants move into natural-gas fields to fuel their AI ambitions, and of the tech industry’s willingness to go it alone for power generation.

“Our agreement with Microsoft through Project Kilby represents Chevron’s unique ability to deliver power to AI customers with certainty, speed and at a competitive cost, leveraging Permian natural gas supply, infrastructure and our proven execution capabilities,” said Jeff Gustavson, president of Chevron’s New Energies unit.

The deal cements Chevron’s lead in the race among major oil companies to bank on the data-center boom. Another big contender, Exxon Mobil, late last year partnered with NextEra Energy to develop a 1.2-gigawatt gas-fired power plant that could come equipped with carbon-capture technology. At the time, NextEra said the companies were in talks with a potential data-center customer.

Rather than plugging into the Texas power grid, Project Kilby will have its own on-site power plant fueled by Chevron’s local natural-gas production. It will connect to the power grid at a later date and plans to sell excess generation into the Texas power market.

“The ability to have a firm power resource for the Texas grid is something I think everyone would welcome,” said Chris James, founder and chief executive of Engine No. 1 and Joulent.

The site is about 20 miles south of Pecos, where Chevron has been producing oil and gas for years.

Joulent already had been working with GE Vernova, which builds gas turbines in high demand for power plants. Chevron teamed up with them last year and said the companies were in negotiations with a then-unnamed customer that was eventually revealed to be Microsoft.

“AI and cloud are advancing at a pace that requires a new level of coordination between energy and infrastructure,” Noelle Walsh, Microsoft president of cloud operations and innovation, said in a statement.

Soaring electricity demand has revealed the limitations of the power grid and its supply chains.

AI training requires city-size amounts of electricity delivered to a single site, with a high rate of consumption around the clock. That requires complex engineering studies and upgrades in transmission equipment that take years to build and deliver. Wait times for electric service have stretched beyond five to seven years in many places.

The idea that data centers must BYOP, or “Bring Your Own Power,” if they want quicker access to electricity, has taken hold across the industry, though it is a costly and challenging workaround to a grid connection, which is considered more reliable.

Developers of about a quarter of all data-center capacity in the works plan to build power on site, according to data provider Cleanview. It is tracking 59 such data centers with a combined capacity of about 90 gigawatts—about enough to power Texas on the hottest day of the year.

Project Kilby would start delivering power in late 2028, with a full build-out of the site continuing into the 2030s, James said.

Going without a grid connection means the project requires an overbuild of power equipment and a large battery storage system to maintain reliability. Solar power could be added later, too, given that West Texas is one of the best spots in the country for it, James said.

The engineering challenges of building “behind-the-meter” projects have been underestimated but can provide companies with computing power more quickly and avoid cost impacts to other ratepayers, James said.

“If we’re going to build the amount of compute that we need, this is going to have to be a very large part of the solution,” James said.

He expects to see more projects moving to West Texas.

“We think the Permian in particular is a place where we’re going to see growth for a very long time,” he said. “This should be the Northern Virginia kind of equivalent for AI compute.”

Appeared in the June 23, 2026, print edition as ‘Chevron To Power Microsoft AI Site In Texas’.